Our Projects

Critical Issues of the Project

Land Acquisition : As per signed Joint Memorandum dated 12.12.2023 under Clause 10.3.1 of Concession Agreement (CA), the % length / land handed over 85%, however, physical possession of land is available to the Concessionaire is 27.824 km that too in bits and pieces which constitutes 48.26% of the total project length. The same informed and requested Authority to handed over hindrance free land as per the provisions of the Concession Agreement by the Concessionaire vide letter no. GBHPL/AIPL/DB_NH114A/2023-24/119, dated 20.03.2024.

Approval of COS-01 : The Concessionaire vide letter no. GBHPL/AIPL/DB_NH114A/2023-24/54 dated 06.02.2024 has submitted proposal for Change of Scope -01 (COS-01) for VUP Ch. 89+027 & VUP Ch. 128+118 instead of LVUP’s as per Schedule-B of Concession Agreement. The IE has review the proposal submitted by Concessionaire and raised observations vide their letter no. ARMENGE/NHAI/JH/IE/Basukinath-Deoghar/2023/5025, dated 12.02.2024. The Concessionaire is hereby requesting to give the In-Principle approval as discussed in the various progress review meeting with IE and Authority.

Sr. No.

Location

Original Scope as per CA

Scope as per COS

1.

89+027

LVUP with RE WALL

VUP with RE WALL

2.

124+245

LVUP

LVUP with RE Wall

3.

128+115

LVUP

VUP with RE Wall

Backdated Appointed Date : The Concessionaire vide letter no. GBHPL/AIPL/DB_NH114A/2023-24/28 dated 28.12.2023 has requested to consider the appointed date from 26.12.2023 instead of 12.12.2023.

Proposed Highway & Structure at Glance

Brief Scope of works

Sr. No.

Structures/Facilities

Unit

Details

1

Length of the Project

Km.

45.159

2

Design Speed

Kmph

100

3

Type of Pavement

-

Flexible Pavement (20 years design life)
Flexible Pavement composition approved (MCW, 70 MSA design traffic) - BC - 40 mm, DBM - 50 mm, WMM with Geogrid.
Rigid Pavement for Toll Plaza (30 years design life)
Rigid Pavement composition approved (MCW) PQC - 280 mm, DLC - 150 mm, GSB - 150 mm

4

Length of Slip/Service Road

Km.

Slip Road : 13.252 Km. & Service Road =4.210 Km.

5

Road Over Bridge

Nos.

2

6

Major Bridge

Nos.

-

7

Interchange

Nos.

-

8

Flyover

Nos.

1

9

VUP

Nos.

8

10

LVUP

Nos.

8

11

SVUP

Nos.

8

12

Minor Bridges

Nos.

14

13

Culverts

Nos.

Box Culvert : 136 & Hume Pipe Culvert : 01 (1200 mm dia.)

Base Camp, Laboratory & Plants

Sr. No.

Base Camp (Approximate Area of Land Purchased / leased)

Laboratory / Plants

Location

Status

1

Base Camp – I

Laboratory I

 Badajharna @ Km 119+000  RHS

Functional

2

Crusher Plant

Quarry & Crusher Unit – IV, 250 TPH

Badajharna @ Km 119+000  RHS

Production In Progress

3

RMC Plant-I

Con. Mix. Plant I
(60 Cum/Hrs)

Badajharna @ Km 119+000  RHS

Production In Progress

4

RMC Plant-II

Con. Mix. Plant II
(30 Cum/Hrs)

Km 106+595

Production In Progress

5

WMM Plant-I

WMM Plant – I (200 TPH, ASHISH)

Badajharna @ Km 119+000  RHS

Production In Progress

6

HM Plant-I

Hot Mix Plant – I (120 TPH, MARINI)

Badajharna @ Km 119+000  RHS

Ready for Production