Highway Progress

 

Unit

Scope

Executed

Balance

% achieved

Bypass

 

 

 

 

 

EMB Top

Km

56.292

8.50

47.792

15.10%

SG Top

Km

56.292

5.08

51.212

9.02%

GSB

Km

56.292

4.45

51.842

7.91%

WMM

Km

56.075

0

56.075

0%

DBM

Km

56.075

0

56.075

0%

BC

Km

56.075

0

56.075

0%

Existing

 

 

 

 

 

EMB Top

Km

32.298

0

32.298

0%

SG Top

Km

32.298

0

32.298

0%

GSB

Km

32.221

0

32.221

0%

WMM

Km

31.801

0

31.801

0%

DBM

Km

31.801

0

31.801

0%

BC

Km

31.801

0

31.801

0%

Service Road

 

 

 

 

 

Non Bitumeninious

Km

34.424

0

34.424

0%

 Bitumeninious

Km

34.424

0

34.424

0%

Highway Progress


Structure Progress


Sr. No.

Str. Type

Unit

Scope

In Progress

Completed

Balance

Remarks

1

ROB

Nos.

2

 

 

2

 

2

Flyover

Nos.

1

 

 

1

 

3

Minor Bridge

Nos.

14

 

 

14

 

4

VUP

Nos.

8

4

 

4

 

5

LVUP

Nos.

8

2

 

6

 

6

SVUP

Nos.

8

4

 

4

 

7

Box culvert

Nos.

136

17

13 

106

13 Box Culverts completed, 656 Nos. of Precast segment casted

8

Re Wall Facia

Sqm.

90,000

 

25902.5

64097.5

 



Precast Work Status


Sr. No.

Description of work

Unit

Scope

Executed up-to-date

% Achieved

Remarks

BEAMS

 

Planks

SVUP_7 Mtr

Nos

336

105

31.25%

 

LVUP_12 Mtr

Nos

336

81

24.11%

 

 

 TOTAL

 

 

672

186

27.68%

 

MISCELLANEOUS

 

Box Segment

 2X2

Nos.

3,029

656

21.66%

 

 

Friction Slab Crash Barrier

Nos.

18,360

-

-

 

 

RE Blocks

Nos.

6,73,800

2,45,042

36.37%

 

 

RE Panel

Nos.

10,345

1511

14.61%

 



Utility Shifting & Tree cutting Status


Current Status

Status of Tree Cutting work

Dumka Tree cutting permission granted (Tree Cutting work in Progress, Apprrox. 56% of Tree cutting completed)

Deoghar Tree Cutting Permission granted (Tree Cutting work in Progress, Apprrox. 14% of Tree cutting completed)

Utility Shifting (Electrical)

Supervision charges paid on date  04 Dec. 2023 (Utility Shifting work in Progress)