Authority |
National Highway Authority of India |
|||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Concessionaire |
M/s. Gawar Basukinath Highway Pvt. Ltd. |
|||||||||||
EPC Contractor |
M/s. Gawar Construction Limited (Allone Infra Pvt. Ltd.) |
|||||||||||
Independent Engineer |
Armenge Engineering Pvt. Ltd. In JV with Chaitanya Projects Consultancy Pvt. Ltd. |
|||||||||||
Name of Project |
Four – Laning of Gawar Basukinath Highways Pvt. Ltd. Section of NH 114 A For Design Km. 85+081 To Km 130+240 (Design Length-45+159 Km) Under NHDP Phase –IV In State of Jharkhand on Hybrid Annuity Mode |
|||||||||||
Construction Period |
730 days |
Maintenance Period |
15 years from PC/CC |
|||||||||
Project Length |
45.159 Km. |
Bid due date |
20.10.2022 |
LOA date |
17.03.2023 |
Appointed date |
12.12.2023 |
Scheduled date of completion |
10.12.2025 |
|||
Agreement Signing date |
11.05.2023 |
|||||||||||
Bid Project Cost |
Rs. 999.00 Cr. |
|||||||||||
Physical Progress |
4.06% |
|||||||||||
Project Milestone No./Financial Progress |
1st @20% (160 Days) / 199.80 Cr. |
2nd @35% (360 Days) / 349.65 Cr. |
3rd @75% (485 Days) / 749.25 Cr. |
Schedule Completion date @100% (730 Days) / 999.00 Cr. |
||||||||
Scheduled Milestone date |
19.05.2024 |
05.12.2024 |
09.04.2025 |
10.12.2025 |
||||||||
Payment Milestone @ 4% of Adjusted BPC on the achievement of Physical Progress @ 5%, 10%, 20%, 30%, 40%, 50%, 60%, 70%, 80% & 90%. |