Highway Details

Sl. No.

Types of Equipment

Total (Nos.)

1

Excavator

25

2

Soil Compactor

19

3

Tendom

2

4

JCB

10

5

Loader

4

6

Hydra

7

7

Motor Grader

16

8

DG

14

9

Tipper

104

10

Transit Mixer

10

11

Tractor

8

12

Forklift

3

13

Bitumen Sprayer

2

14

Diesel Tanker

6

15

Water Tanker

20

16

Mixture Machine

1

17

RMC Plant

2

18

Mesto Crusher

2

19

DBM Plant

1

20

RE Block & RE Pannel making machine (Apollo Brick Plant)

2

21

WMM Plant

1

22

Piling Rig

1

23

Gantry Crane

1

24

Steel Bar Cutter

1

25

Trailor

4

26

Weighbridge

2

Total

268



Land Acquisition Status


As per actual site condition
(Please refer our Letter No. GBHPL/AIPL/DB_NH114A/2023-24/119, dated:20.03.2024)

Sl. No.

Description

 

Length (km.) for BHS

%

Remarks

1

Total Length of the Project

A

45.159

100.00%

 

2

PROW yet to be Hand over

B

6.860

15.19%

As per Annexure-A

3

Works has been stopped by the farmers / Local Villagers due to Land Acquisition issues etc.

C

9.000

19.93%

As per Annexure-B

4

Length effected due to Religious Structures

D

0.350

0.78%

As per Annexure-C

5

Length effected due to various Structures / Obstructions in handed over Length

E

7.154

15.84%

As per Annexure-D

6

Total Hindrance free land yet to handover to the Concessionaire

F

23.364

51.74%

B+C+D+E



Work Status as per Availability of Hindrance Free Land

  • Total Project Length = 90.318 (2-lane Km.)
  • Hindrance Free Land Available = 43.590 (2-lane Km.)
  • Execution work taken-up in the Hindrance free land = 32.120 (2-lane Km.)
  • Earthwork Completed up to Embankment top = 8.500 (2-lane Km.)
  • Earthwork Completed up to Subgrade top = 5.080 (2-lane Km.)
  • Granular Sub Base Completed = 4.450 (2-lane Km.)