Sl. No. |
Types of Equipment |
Total (Nos.) |
---|---|---|
1 |
Excavator |
25 |
2 |
Soil Compactor |
19 |
3 |
Tendom |
2 |
4 |
JCB |
10 |
5 |
Loader |
4 |
6 |
Hydra |
7 |
7 |
Motor Grader |
16 |
8 |
DG |
14 |
9 |
Tipper |
104 |
10 |
Transit Mixer |
10 |
11 |
Tractor |
8 |
12 |
Forklift |
3 |
13 |
Bitumen Sprayer |
2 |
14 |
Diesel Tanker |
6 |
15 |
Water Tanker |
20 |
16 |
Mixture Machine |
1 |
17 |
RMC Plant |
2 |
18 |
Mesto Crusher |
2 |
19 |
DBM Plant |
1 |
20 |
RE Block & RE Pannel making machine (Apollo Brick Plant) |
2 |
21 |
WMM Plant |
1 |
22 |
Piling Rig |
1 |
23 |
Gantry Crane |
1 |
24 |
Steel Bar Cutter |
1 |
25 |
Trailor |
4 |
26 |
Weighbridge |
2 |
Total |
268 |
Designation |
Total Manpower |
---|---|
Technical Staff |
|
Project Manager |
1 |
Dy. Project Manager |
2 |
Structure Section |
14 |
Highway Including Surveyor |
37 |
Quality Control |
14 |
Survey Section (Total Station Group) |
8 |
Planning & QS |
7 |
Total |
83 |
Supporting staff |
|
Account, HR, Liaison |
12 |
Mechanical Section |
10 |
Supervisors (Site execution) |
62 |
Store, Purchase |
19 |
Mechanical (Driver, Operator, Helper) |
310 |
Crusher |
8 |
Total |
421 |
Total (Nos.) |
504 |
Sl. No. |
Descriptions |
Concessionaire submission |
Authority Forwarding to IE |
IE Observation | Concessionaire Compliance |
IE Concurrence | GFC Drawing submission by Concessionaire |
Status | Remarks | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Letter No. |
Date |
Revision |
Letter No. |
Date |
Letter No. |
Date |
Letter No. |
Date |
Revision |
Letter No. |
Date |
Letter No. |
Date |
||||
1 |
Pavement Design Report |
59 |
13-2-24 |
R0 |
- |
- |
5076 |
24-2-24 |
82 |
1-3-24 |
R1 |
5126 |
11-3-24 |
105 |
11-3-24 |
|
IE instructed to get PDR vetted by IIT vide letter No. 044, dated 19.04.2024. |
2 |
Plan & Profile (MCW) |
29 |
30-12-23 |
R0 |
604 |
9-2-24 |
5027 |
12-2-24 |
68 |
19-02-24 |
R1 |
5121 |
9-3-24 |
103 |
9-3-24 |
|
|
5271 |
11-4-24 |
|
|
|
|
||||||||||||
3 |
Plan & Profile (Slip/ Service Road) |
29 |
30-12-23 |
R0 |
604 |
9-2-24 |
5027 |
12-2-24 |
68 |
19-02-24 |
R1 |
5121 |
9-3-24 |
103 |
9-3-24 |
|
|
5271 |
11-4-24 |
|
|
|
|
||||||||||||
4 |
Drainage Plan |
29 |
30-12-23 |
R0 |
604 |
9-2-24 |
5027 |
12-2-24 |
68 |
19-02-24 |
R1 |
5121 |
9-3-24 |
103 |
9-3-24 |
|
|
5271 |
11-4-24 |
|
|
|
|
||||||||||||
5 |
Highway Misc. Drawings |
29 |
30-12-23 |
R0 |
604 |
9-2-24 |
5027 |
12-2-24 |
68 |
19-02-24 |
R1 |
5121 |
9-3-24 |
103 |
9-3-24 |
|
|
5271 |
11-4-24 |
|
|
|
|
||||||||||||
6 |
Box Culverts |
29 |
30-12-23 |
R0 |
604 |
9-2-24 |
5075 |
24-2-24 |
87 |
4-3-24 |
R1 |
5130 |
11-3-24 |
107 |
12-3-24 |
|
|
7 |
Flyover |
29 |
30-12-23 |
R0 |
604 |
9-2-24 |
|
|
|
|
|
5268 |
11-4-24 |
|
|
Provisionally Approved |
|
8 |
LVUP |
29 |
30-12-23 |
R0 |
604 |
9-2-24 |
|
|
|
|
|
5268 |
11-4-24 |
|
|
Provisionally Approved |
|
9 |
SVUP |
29 |
30-12-23 |
R0 |
604 |
9-2-24 |
|
|
|
|
|
5273 |
12-4-24 |
|
|
Provisionally Approved |
|
10 |
VUP |
29 |
30-12-23 |
R0 |
604 |
9-2-24 |
|
|
|
|
|
5268 |
11-4-24 |
|
|
Provisionally Approved |
|
11 |
ROB |
29 |
30-12-23 |
R0 |
604 |
9-2-24 |
|
|
|
|
|
|
|
|
|
Approval Awaited |
|
12 |
MNB |
29 |
30-12-23 |
R0 |
604 |
9-2-24 |
|
|
|
|
|
5273 |
12-4-24 |
|
|
Provisionally Approved |
|
13 |
Working Pile Drawing for Flyover Ch. 121+070 |
32 |
3-1-24 |
R0 |
604 |
9-2-24 |
28 |
20-3-24 |
123 |
20-3-24 |
|
|
|
|
|
Approval Awaited |
|
14 |
Test Pile Drawings for ROB CH. 121+535 & ROB Ch. 120+550 |
40 |
12-1-24 |
R0 |
604 |
9-2-24 |
|
|
|
|
|
|
|
|
|
Approval Awaited |
|
15 |
RE Wall Design & Drawings |
56 |
8-2-24 |
R0 |
- |
- |
|
|
|
|
|
|
|
|
|
Approval Awaited |
|